2. Project Management & Joinery Execution
This guide covers how Edge Home Solutions manages the full execution lifecycle of wardrobe, cabinetry, and kitchen projects from site survey to final handover.
1. The 12-Task Joinery Execution Pipeline
Every interior fitting project uses the standardized Custom Interior Fitting (Wardrobe / Kitchen / Cabinetry) template:
[Phase 1: Survey & Design]
├── Task 1: Site Laser Survey & Technical Measurement
├── Task 2: 3D Architectural CAD Render & Material Selection
└── Task 3: Client Design Sign-off & Contract Approval
[Phase 2: Workshop Joinery]
├── Task 4: Material Procurement & Hardware Sourcing
├── Task 5: Panel Precision Sizing & CNC Milling
└── Task 6: PVC Edge-Banding & Workshop Carcass Pre-Assembly
[Phase 3: Delivery & Site Installation]
├── Task 7: Site Delivery & Safe Material Staging
├── Task 8: Carcass Mounting, Leveling & Wall Anchoring
├── Task 9: Shutter Doors, Tandem Drawers & Hardware Alignment
└── Task 10: Countertop Templating, Cutting & Appliance Fitment
[Phase 4: Finishing & Handover]
├── Task 11: Final Polish, Soft-Close Calibration & Clean-up
└── Task 12: Joint Snag Inspection & Client Sign-off Handover2. Launching a New Fitting Project
- Go to Projects → Project → + Add Project (https://erp.edgehomesolutions.co.ke/desk/project).
- Fill in project details:
- Project Name: Format as
[Location/Client] - [Fitting Type](e.g., Kilimani Penthouse - Modular Kitchen & Master Wardrobes). - Company:
Edge Home Solutions. - Customer: Select client name.
- Project Type: Select
Modular Kitchen,Built-in Wardrobes, orFull House Interior Joinery. - Project Template: Choose
Custom Interior Fitting (Wardrobe / Kitchen / Cabinetry). - Expected Start Date: Scheduled survey date.
- Estimated Costing (KES): Total project budget.
- Project Name: Format as
- Click Save.
- Result: ERPNext immediately generates all 12 tasks linked together with estimated durations.
3. Managing Tasks & Assigning Fitters
- In the Project, switch to the Tasks tab or Gantt view.
- Open a task (e.g., Task 5: Panel Precision Sizing & CNC Milling).
- Assign to the workshop lead carpenter or CNC technician using the Assigned To button.
- Record actual progress:
- Status: Update from
Open→Working→Completed. - Timesheets: Fitters can log workshop hours against the project to track exact labor costs.
- Status: Update from
4. Snagging & Final Handover Protocol
During Task 12: Joint Snag Inspection & Client Sign-off Handover:
- Lead installer and client walk through the installed units.
- Complete the quality checklist:
- [ ] Soft-close hinges calibrated and closing smoothly without rubbing.
- [ ] Drawer slides running flush with soft-closing dampening engaged.
- [ ] Countertop joints sealed and silicone waterproofed.
- [ ] Kickplates and filler scribes cleanly secured to walls and floor.
- [ ] Protective films and sawdust cleaned.
- Client signs the Handover Acceptance Form.
- Mark Task 12 as
Completedand set Project Status toCompleted. - Trigger Milestone 3 (10% Final Retention Invoice).